The $309.26 million electricity transmission line project between Kenya and Tanzania, a cornerstone of East African energy integration, faces significant delays.
Originally slated for completion in December 2023, the project now aims for an April 2024 commissioning at the earliest, raising concerns about regional power exchange and economic development.
The 507.5-kilometer transmission line, designed to transfer up to 2,000 MW of power, is a critical link in the Eastern Africa Power Pool (EAPP).
It aims to facilitate power exchange between Kenya and Tanzania while also connecting Ethiopia’s vast hydropower resources. This project is vital for enhancing energy security and fostering economic growth across the region.
However, the project has encountered several obstacles. Kenya Electricity Transmission Company (Ketraco) and Energy Cabinet Secretary Davies Chirchir have cited compensation issues for affected landowners and legal disputes with contractors as primary reasons for the delay.
These challenges have not only pushed back the timeline but also raised questions about project management and governance in large-scale infrastructure developments.
The implications of this delay are far-reaching. It directly impacts the power-sharing agreements between Kenya and Tanzania, potentially sidelining Kenya as Uganda progresses with its own interconnector project.
This setback could have significant economic consequences, affecting energy access and industrial development across East Africa.
The delay also poses a challenge to the broader regional power integration plan.
The East African Power Pool, which aims to create a unified electricity market, now faces a significant obstacle.
With Kenya and Tanzania unable to exchange power as planned, neighboring countries’ projects and partnerships may also be affected.
This domino effect could slow down the entire region’s progress towards energy security and economic growth.
Financiers, particularly the African Development Bank (AfDB), have expressed concerns about the project’s delays.
The AfDB, a major backer of the transmission line, has called for expedited negotiations to resolve outstanding issues.
The bank emphasizes the importance of finalizing agreements for power exchange and maintenance of the interconnected grid, highlighting the project’s critical role in regional development.